Sr.No | Details | Time to complete the work | Concern Officer & Address | Remarks
|
1. | Applications for consent under Water, Air & Hazardous Waste will be available on Rs.50/- in Sub-Regional Offices | Office Working Days 11:00 A.M. to 1:00 P.M. & 2:00 P.M. to 4:00 P.M. | Sub-Regional Officers Office | |
2. | Acceptance of application & Receipt | Same Day | Sub-Regional Officers Office | |
3. | Time to Communicate the discrepancies to applicant | Three days | Sub-Regional Officers Office | |
Time for Verification of site & other Technical details after Completion of discrepancies | Fifteen days | Field Officer Of Concern Sub-Regional Office | ||
5. | Time for Grant of Consent after verification (Based on Capital Investment) | |||
a | Simplified Consent(Pollution free SSI) | Three days (After completion of Descripancies & Verification Report) | Sub-Regional Officer | |
b | Green Consent- Investment | |||
Rs.3 Crores | Six days | Sub-Regional Officer | ||
Rs.3 Crores to 10 Crores | *One & Half Month | Regional Officer | ||
Rs.10 Crores to 500 Crores | * Two Months | Member Secretary, M.P.C.Board, Mumbai | ||
Above Rs.500 Crores | * Consent Appraisal Committee M.P.C. Board, Mumbai | |||
c | Orange Consent-Investment | |||
Upto Rs.5 Crores | * One & Half Month | Regional Officer | * One Month After receipt of minutes of Consent Appraisal Committee | |
Rs.5 Crores to 100 Crores | * Two Months | Member Secretary, M.P.C.Board, Mumbai | ||
Above Rs.100 Crores | * One Month After receipt of minutes of Consent Appraisal Committee | * Consent Appraisal Committee M.P.C.Board, Mumbai | ||
d | Red Consent-Investment | |||
Upto Rs.15 Crores | * Two Months | Member Secretary, M.P.C.Board, Mumbai | ||
Above Rs.15 Crores | * Consent Appraisal Committee M.P.C.Board, Mumbai |